Relocation Progress Updates

1 May 2017

A significant milestone was achieved on the afternoon of Sunday 30 April! The main steel rails which make up the main track loop were welded to complete one single 900+ metre continuous loop. Woohoo!

It was a very productive day, our Members began at 7:30am and finished at 6pm. As wel as working on our new main track loop, our (qualified!) electrician/ Member completed installing the lighting and power outlets to four of the five bays in our new storage shed.

Tasks we still need to achieve before we can reopen to public passengers include:-
– The new rails on the main track loop need to have their sleepers attached and screwed, and then the stone ballast beneath is shaped so that the track is smooth and safe for trains to run on with passengers. This takes much time and persistence.  Thanks to the assistance from our local PCYC team;
– The spur line from the main loop to the turntable needs to be built;
– The steaming bays need to be installed; and,
– We still have one structure to relocate from the old site at Kearney Springs Historical Park to Lemway Park.
– And all track work needs to be checked to ensure that it is safe for passenger hauling.

Toowoomba Regional Council still has some fencing and signage to install, and some finishing touches to add to the landscaping. Thank you to Toowoomba Regional Council and their staff for their continuing support.

  • Cutting the steel rails to insert the last curve …
  • Welding the last curve into the new main 900+ metre loop … 
  • Welding a six metre length of rail … 
  • Installing the conduit and wiring for lighting and power outlets … 

We are often asked, “When will we be running and giving rides at our new location??”  … We are still hoping that it will be Spring this year, or sooner, if we can.

There are still a lot of tasks to do which are dependent on the ability of our members and volunteers to continue dedicating their time and efforts … and the weather!  We will keep you posted about our progress … it is becoming even more exciting!

If you have any questions please do not hesitate to Contact Us.

 

19 March 2017

It is timely for a quick update on how the relocation from Spring St to Lemway Ave is progressing.
Toowoomba Live Steamers (TLS) members (with assistance from PCYC) have installed about two thirds of the gravel ballast and steel rails for the new track, with about half the length of the track also being levelled so that it is smooth and safe for trains to eventually run on.

Having completed the earthworks and drainage, Toowoomba Regional Council has now completed the new station building and will be adding the finishing touches to some fencing at the station and landscaping, so that TLS can then finish off the last portion of the new track up to the station.
Thank you to Toowoomba Regional Council and their staff for their continuing support.

Our Compound area is slowly becoming more familiar … we have installed the turntable (for turning our loco’s), and more of our gear is progressively being relocated into our new shed.

Have included a few photos of …

  • the new station …
  • the gravel ballast waiting for levelling & steel rails …
  • some completed track … 

When will we be running and giving rides at our new location?? … It will depend on the progress of TRC completing their work, and the ability of our members and volunteers to continue dedicating their time and effort towards tasks for the relocation … and the weather! We are hoping that it might be Spring this year … or sooner, if we can. We will keep you posted about this … it will be exciting!

And, for those who may have been trying to access our website … we apologise, we are having technical difficulties with its hosting and are endeavouring to have it back up and running as soon as we can.

Please feel free to Like and Share, and if you have any questions please do not hesitate to contact TLS.
We also have a new email address – twmbalivesteamers@gmail.com

Until next update.

=============================================================

21/11/2016

Just a quick update.
After the November Monthly Meeting yesterday Sunday 20th Nov some of our members did a walk around the new site and inspected our new Loco/Carriage/Meeting Room Shed.
We have paid for an extra bay on this new shed to allow for possible asset expansion in the future.
The projected completion of the complex is now post March 2017, unfortunately. As we approach the Christmas period work by Council will soon cease with recommencement of work in probably late-ish January 2017 and the station construction may begin around this time.
This is about all that we can report on at present.

Until next time, as always, may your lights be green and your rails straight.

tlsi-loco-shed

tlsi-k

Looking North to the Grove of Trees.

tlsi-j

tlsi-i

Looking North Towards the Northern Loop

tlsi-h

Looking South from the Station Area

tlsi-g

Excavation of the Station and Platform.

tlsi-f

Northern Loop Track Bed

tlsi-d

Eastern End of the Loco Shed Slab

tlsi-c

Western End of the Loco Shed Slab

tlsi-b

Southern Loop Area

tlsi-a

Southern Loop Area

=======================================================

Update Time

Work has begun on our relocation to our new location in Lemway Park.
Graham and various members have been cutting the track into 6 metre lengths and with the wonderful help of men from the PCYC those sections have been lifted and stacked ready for removal to Lemway Park.
I have included some photos of the progress. It is a tad sad but knowing that we will have a better railway for your enjoyment makes it all worthwhile…….

AND IT WILL BE BAT FREE.

Kearney1

Kearney11Kearney2Kearney3Kearney4Kearney5Kearney6Kearney7Kearney8Kearney11Kearney12Kearney8Kearney9Kearney10Kearney11Kearney13Kearney14Kearney15

=============================================================

September 2016

Here are some pics of what is happening in Lemway Park.
Our apologies to the public who use the park as it has been fenced off today. The council has fenced the area to make it safe while works are implemented.

Lemway 4Lemway 1Lemway 6Lemway 5

We will keep you posted about further happenings.

Until next time…….

——————————————————————————————————————–

Link to Toowoomba Regional Council’s webpage about their works for Toowoomba Live Steamers  ->TrcLogo-Portrait[1]

——————————————————————————————————————–

The aerial view below is the latest PROPOSAL for the new track layout. The new track will have approximately 900+metres of mainline as against 656 metres at the present site. This should make for an interesting and enjoyable ride.

 TLSI Proposed Track

================================================================